METHOD STATEMENT FOR PIPE JACKING WORK

Nochu

Thành viên rất năng động
Tham gia
15/10/20
Bài viết
117
Điểm thành tích
16
Tuổi
21
Nơi ở
Hồ Chí Minh
INTRODUCTION

1.1 Introduction


The Vung Ang II thermal power plant is part of the Vung Ang thermal power center and is the second complex of the coal-fired electricity generating plant located in the Vung Ang industrial zone, Ky Loi commune, Ky Anh district, Ha Tinh province in Vietnam. Vung Ang II will be constructed adjacent to Vung Ang I which is already in operation. It consists of two turbines with a total capacity of 1,200 MW. Both will be fueled by imported anthracite, hard coal.

1.2 Abbreviation and definition

The Owner Vung Ang II Thermal Power LLC

The Contractor DHI-SCT Joint Venture

HSE Health, Safety and Environment

MS Method Statement

RA Risk Assessment

PPE Personal Protective Equipment

QA/QC Quality Assurance/Quality Control

1.3 Scope of work

To install the CW underground pipeline of Vung Ang 2 Thermal Power Plant at crossing area with Vung Ang 1 belt conveyor by pipe jacking pressing method.

1.3.1 Constructing of 04 CW pipelines with Diameter 2700mm


Constructing-of-04-CW-pipelines-with-Diameter-2700mm.jpg


Number of CW pipelines can be changed with 2 pipelines (DN 3700) at the detail engineering stage

2 OVERVIEW

CW pipe DN2700 to install underground by Pipe jacking method.


Plan-View-of-Construction-Location.jpg


Plan View of Construction Location


Table 1.1 Contents of work

No

Items

Method statement

Quantities

Note

A

Shaft construction

 

 

1​

Driving and extract steel sheet pipe Larsen IV

Use Silent Piler(100-150T)

 

2​

Soil improvement for bottom of shaft

Jet Grouting D1800

2shaft​

 

3​

Soil improvement for entrance of launching and arriving shaft

Jet Grouting D1200

 

4​

Strut installation

Lifting and installing

 

5​

Soil Excavation

Use excavator

 

B

Pipe jacking construction

 

 

1​

Supply DN2700 pipe

 

 

2​

Installation CW pipe DN2700

Pipe Jacking

40m​

 


3 METHOD STATEMENT

3.1 Shaft construction

3.1.1 Construction sequence


Screenshot (465).png


3.1.2 Sheet pile construction

a. Preparation work

Approved all documents

Mobilization equipment and materials.

b. Survey work

Use total station machine to setting up.

Marking point by paint on the site.

Checking underground utilities.

c. Sheet pile driving

Checking weather before construction

Welding sheet pile with length of design.

Use crane to lifting sheet pile for driving.

Sheet pile driving with checking alignment by water ruler.

d. Cleaning after construction

Remove all materials and rubbish,

Keep clean of site.

e. Construction sequence


Screenshot (467).png


Xem tiếp METHOD STATEMENT FOR PIPE JACKING WORK >>
 

File đính kèm

  • Plan-View-of-Construction-Location.jpg
    Plan-View-of-Construction-Location.jpg
    128,4 KB · Đọc: 82

Tải bộ cài phần mềm Dự toán GXD, Đấu thầu GXD, Thanh Quyết toán GXD, Quản lý chất lượng GXD. Dành cho người mua bản quyền
Kích để xem khóa học Dự toán công trình
Kích để xem khóa học Dự toán công trình
Phần mềm quản lý chất lượng công trình QLCL GXD
Tìm hiểu khóa học Thanh Quyết toán GXD

Các bài viết mới

Top